Shipboard PMS

Demonstration of the functionality and normal operation of the Shipboard Power Management System (PMS) model example

Introduction

This marine microgrid model demonstrates an example of a Shipboard Power Management System (PMS) and its several functions. The ship’s main power supply comes from two Diesel Gensets (DG), which feeds into several key groups of loads in the model: constant loads (e.g. the Lights and Auxillary (AUX) loads), variable loads (e.g. Fans & Pumps), and the motor loads (propulsion and thruster). The microgrid consists of multiple buses that are mutually connected with bus breakers, and where some parts are implemented as RL sections. The marine microgrid can be divided into two sections with different voltage levels – 230V and 440V – which are connected via three transformers (Figure 1).
Figure 1. Marine microgrid with PMS

Model description

The power supply for this microgrid comes from DG1 and DG2, where the nominal power of each generator is 2.69 MW, resulting in up to 5.38 MW combined. Both DGs receive commands either from the PMS or manually from the SCADA panel.

Commands to the DGs from the SCADA, (such as turning the generators on and off, providing reference active or reactive power, etc.) can be conducted either from root panel or from DG’s subpanels. Operating from the DG subpanel gives a larger variety of commands as well as insight in the DG behavior.

To manage the power flow manually, check the Force Local Control checkbox in the DG2 Control widget. This prevents the PMS from overriding commands given to DG2.

Loads are implemented in either variable form or constant form. The Lights and AUX Loads are considered constant loads, which are placed in various places of the model. Variable loads

Fans pumps are implemented as variable RL loads using time varying components. They can be enabled or disabled by closing or opening the breaker in the Fans and Pumps group widget. Also, the total power that the Fans and Pumps consume can be set in the same widget, as measured by percentage of total load.

Thrusters are modeled as VBR (Voltage Behind Reactance) induction machines with a mechanical solver in the C function and a Soft Starter between it and the busbar. Control of the thrusters is conducted from the SCADA panel. If Soft Starter reset is not initiated, then during the next thruster startup, full voltage will be immediately conducted through the Soft Starter. This is because the Soft Starter is modeled as an ideal transformer whose turns ratio changes during the startup, so if the reset is not initiated than its turns ratio will stay 1:1. By changing the Blade Pitch you can load the motor with a given percentage of nominal torque, while Ramp Enable will limit the rate of change in torque given to the machine.
Figure 2. Thrusters control in SCADA

The propolusion unit is composed of a Passive Rectifier and a Variable Resistor (controlled by signal processing). This is the only unit that contains a converter-based component. These form an abstraction of a two-level motor drive and an induction motor.

Simulation

The purpose of PMS is to control the generators and the breaker in a way that enables power sharing as well as prevention of DG overload. The PMS measures the active and reactive power of the DGs, the states of the DG breakers, and the state and the measured and calculated synchronization parameters of the Main SB 440V CB breaker. Based on the data received, the system decides on what commands to give to DG1, DG2, and the Main SB 440V CB.

The PMS monitors the power output by DG1, and if it exceeds 1.61MW for a sufficient time period, the system starts DG2. Soon after DG2 is on and connected to the busbar, the PMS will start the process of equalizing the power output of DG1 and DG2 until equilibrium is reached. If the joint power output of both DGs falls below 1.75 MW for a sufficient time period, the PMS will command the second DG to turn off. The difference in power demand between when DG2 is off and on is from the additional power demand caused by the snubber losses from operating DG2.

To observe the PMS in operation, DG1 will have to be turned on manually and set to Grid forming mode. Only the thrusters and propulsion are loads that can sufficiently increase the total power consumed by the system to trigger the PMS to start DG2. Connecting the thrusters is followed by large spike in the power consumed by the system (Figure 3); the amplitude of this spike depends on if the Soft Starter was active or not during startup. These spikes will not induce the PMS to turn on the second generator, since they cycle faster than the minimum time required for the PMS to request DG2 to respond to a power shortage.

After connecting and setting up the loads to sufficient values that the combined demand exceeds the power threshold, the PMS will turn on DG2, connect it to the busbar, and start the process of power sharing. This includes the process of equalizing the power output of both DGs, which can be observed in the Active and reactive power widgets, where the PMS gives the same reference Active and reactive power to both generators (Figure 3).
Figure 3. Power sharing – Process of equalizing active and reactive power
If we lower the power consumed by the system, the PMS will turn off the DG2, and leave only DG1 working. Before turning off DG2 it will de-load the power from DG2 and increase the power output of DG1.
Figure 4. De-loading and process of DG2 shutting down
The PMS is also in charge of synchronizing and closing the Main SB 440V CB. To observe this process, both DGs must be turned on and connected to their side of the busbar while the breaker is open. Afterwards, the PMS will initiate the process of synchronization: when phase difference and voltage difference from both sides of the contactor fall within a given range, breaker will receive a signal to close.
Figure 5. Synchronization process
If a three-phase rectifier is connected to the busbar, harmonics will be introduced in the grid, and their impact on the grid will be according to the propulsion load. Power consumed by propulsion is controlled in SCADA by entering its percentage of nominal load.
Figure 6. Currents and voltages on DG output when propulsion is on
Table 1. Minimum requirements
Files
Typhoon HIL files

examples\models\marine power systems\shipboard power

shipboard power.tse,

shipboard power.cus

Minimum hardware requirements
No. of HIL devices 1
HIL device model HIL604
Device configuration> 1

Test automation

We don’t have a test automation for this example yet. Let us know if you wish to contribute and we will gladly have you signed on the application note!

Authors

[1] Dimitrije Jelic